Conceptual Design of the Kura River Reservoir

Overview
Conceptual design of Kura River reservoir: three dam alternatives (271.4 to 650.8M m³) serving 12,000 ha

A large-scale strategic hydraulic engineering conceptual project focused on regulating water resources along the South Caucasus' largest hydrological artery — the Kura River. The primary objective is to secure dependable multi-year irrigation for a 12,000-hectare agricultural command area while providing reliable downstream flood control and regional water storage reserves.

The conceptual engineering framework evaluates three alternative structural configurations:
• Option 1: construction of a 30 m high embankment dam with a crest length of 1,783 m, impounding a reservoir with a total capacity of 271.4 million m³;
• Option 2: construction of a 40 m high dam with a crest length of 2,001 m, creating an impoundment basin with an active storage of 600.5 million m³;
• Option 3: construction of a 50 m high dam with an extended crest length of 2,728 m, generating a maximum reservoir volume of 650.8 million m³.

The technical scope incorporates comprehensive river discharge modeling, sediment deposition assessments, spillway discharge hydraulic sizing, and conveyance scheme optimization for regional irrigation networks.

Project details
Client
“Azerbaijan Melioration and Water Management” OJSC
Location
Republic of Azerbaijan, Kura River basin
Country
Azerbaijan
Category
Hydrotechnical and Melioration Facilities
Duration
1 year
Status
Completed
Location
Republic of Azerbaijan, Kura River basin